A turbine and a generator for the CCGT-250 of Kazanorgsintez PJSC were delivered to Kazan by a special barge along the Volga River. The equipment was manufactured by the general contractor for the construction of the station, Siemens Energy, in the German cities of Erfurt and Berlin. The weight of the gas turbine assembly is 198 tonnes, the weight of the generator assembly is 221 tonnes. The total tonnage of the delivered main equipment exceeds 1,700 tonnes.